Outfall Drain at the beach at Watson Drive: FDOT is considering State/Town/County participation in solving the SR-A1A drainage problem with the Town entering into a JPA with FDOT to fund the improvements (estimated cost is $178,000). FDEP has determined that the proposal complies with FDEP requirements concerning use of the land. County staff is reportedly looking into the possibility of assisting in some, as yet undetermined, manner.
FRDAP Grant/Nance Park: An application for FRDAP monies was sent to FDEP September 5, 2006. Proposed project improvements, costing $50,000, include redecking the boardwalk area between the restrooms and crossover #3, redecking access #4, providing additional sidewalks in the southern end of the park to better move pedestrians and avoid conflicts with vehicles, paving a portion of the parking lot drive-thru area, and providing additional play equipment.
FRDAP Grant/Riverside Park: A FRDAP application was sent to FDEP September 5, 2006. Proposed project improvements, costing $50,000, include a walkway through the park from the handicap parking spaces, interconnecting with the picnic areas, to end across from the sidewalk at Second Avenue; outside binoculars/telescopes (2) at the western end of the pier; and a bench swing.
Dual northbound turn lanes on SR-A1A @ US-192: FDOT has determined that a second northbound left turn lane can be installed within the FDOT right-of-way, which will improve the operation and efficiency of the intersection. The MPO Traffic Operations Committee recommended this project as the third prioritized project and the MPO has indicated in the 2025 Long Range Transportation Plan that this section of SR-A1A will experience severe congestion. FDOT has included $545,993 for the project, which will include mast arms, in the Five-Year Transportation Plan for FY-07. The end result of the project will move traffic and a newly constructed sidewalk to the west side of the right-of-way that lies to the east of the Longboard House. Plans were reviewed with comments having been forwarded to FDOT. The FDOT Tentative Five-Year Plan includes $584,000 for this project. FDOT has combined the project with a similar project in Brevard County and has set a bid letting date of January 31, 2007.
Pedestrian Crosswalk: FDOT expects to respond by February, 2007 to the Town’s request for a pedestrian crosswalk on SR-A1A at Eighth Avenue.
Ernest Kouwen-Hoven Bridge: The FDOT Tentative Five-Year Transportation Plan projects spending $2.3 million in FY-08 to make repairs and fix the expansion joints on the Ernest Kouwen-Hoven Bridge.
Drainage Pipe Replacement: Atlantic Development is replacing failing metal drainage pipe along the east side of S. Ramona Avenue from 8th Avenue to 10th Terrace.
Melbourne Causeway: FDOT has included in the Tentative Five-Year Transportation Plan replacing the easternmost relief bridge (bridge number 700037) and the parallel pair of relief bridges (bridge numbers 700173 & 700175), which are east of the Ernest Kouwen-Hoven Bridge on US-192. The plan includes monies in FY-06 for design and monies in FY-10 ($8.223 million) for construction. For the tentative FDOT Five-Year Plan the construction cost has been projected at $15.7 million. The Brevard County Causeway Vulnerability Study will impact this project but it appears that the Indian River Lagoon North Restoration Feasibility Study will not. A temporary bridge will be constructed south of the existing bridge, which will protrude about 30 feet south of US-192 along Douglas Park. It is not known if the new bridge decks will be elevated above the current bridge decks. Staff has requested that a separated 10-foot bike path be constructed on the bridges for traffic moving in both directions and four-foot bike lanes along the outer lanes of the new bridges. It is expected that the current pedestrian and bicycle traffic thruways will be maintained during construction.
Nance & Sunrise park leases: Staff has requested that the County extend the leases that it has with the State and follow-up with extensions of the County leases with the Town for the properties that the Town operates as Nance Park and Sunrise Park. Both properties have leases that expire in 2037; however, FRDAP requirements stipulate that the Town, when applying for FRDAP grants, have control of the property for at least 30 years. The County is in the process of securing new leases with the State for the two properties.
Right-of-way maintenance: Public Works personnel are trimming vegetation along the various street rights-of-way in the Town to remove vegetation that is hanging over or into the driving surface of Town streets.
Police Vehicles: #8 (SUV) damaged in accident (non-employee driver at fault) is being repaired.
Sunrise Park: Additional parking spaces are to be installed the week of January 8, 2007, along the north side of Watson Drive. A drainage retention area is being situated west of the parking spaces.
Comprehensive Plan/Evaluation & Appraisal Report (EAR): A workshop for the public and Zoning & Planning Board to receive input for development of the EAR to meet State requirements is scheduled for the evening of Tuesday, February 27, 2007.
Melbourne Causeway (south side): FDOT provided the forms to complete the Joint Participation Agreement (JPA) for FY-06 funds to install trees along the south side of the Melbourne Causeway between the Ernest Kouwen-Hoven Bridge and Bridge #700037 (the easternmost relief bridge). The JPA was proposed for $20,100 to install 78 Sabal Palm trees, 11 E. Palatka Holly trees, and 14 Silver Buttonwood trees. The area is approximately 2400 feet in length and is 18 to 20 feet wide (i.e. between the State’s required clear zone and the new bike path). A grant application was provided for the above noted improvements to the Florida Department of Agriculture and Consumer Services for Urban & Community Forestry funds on February 17, 2005, which has been approved and executed. Council determined on April 19, 2005, to adjust the plantings being requested through FDOT to be as follows: 69 Sabal Palm trees, 21 Silver Buttonwood trees, 11 Sea Grape trees, and 11 Gumbo Limbo trees. FDOT and the Town Manager met to review concerns about JPA requirements. FDOT has reviewed the Town’s planting proposal and noted that the requirement for Registered Landscape Architect (RLA) services will be required. FDOT believes that they can address the RLA requirements and then have the Town proceed to have the trees installed through a JPA. Council approved the JPA on January 17, 2006 with FDOT executing the document on February 10, 2006. The landscape architect reviewed the plans with the Town Manager on April 14, 2006, and updated the plans and specifications. Comments from FDOT were due to the landscape architect by the end of the month. A request was submitted to extend the grant completion deadline for the Urban & Community Forestry grant, which was approved extending the deadline to September 30, 2007. FDOT provided the required landscape plans to the Town on August 21, 2006. Council approved the adjustment of trees within the planting space on September 19th. The tree allocation is for 75 Sabal palms of varying sizes, 10 Gumbo Limbo trees, 18 Sea Grape trees, and 14 Silver Buttonwood trees. The project has been bid with notice publication dates of November 16, 2006, and January 4, 2007 and a bid opening date of January 19, 2007.
Mitigation Grant: The County granted approval for the Town to apply for $53,000 in non-local (FEMA) funds for shutters and an emergency generator for Town Hall. The local share is $17,667. The application was sent to the Florida Department of Community Affairs on May 2, 2005. DCA noted that the emergency generator was ineligible for funding. The application is still in process for consideration.
Nance Park: The dumpster enclosure has been relocated.
Public Works has recently painted trash containers along the Melbourne Causeway, repaired and sealed wooden picnic tables in the Nance Park pavilions, and removed the braces supporting the palm trees in the Fifth Avenue median. The supports were added after the palm trees were straightened following hurricanes Frances and Jeanne.
Sidewalk: The County, at the Town’s request, has replaced broken sidewalk along the west side of N. Palm Avenue at Grosse Pointe Avenue.
Hand rails: Wooden hand rails along access #4 in Nance Park and at access #6 (from the parking lot to the boardwalk) at Indialantic Beach Park are in the process of being replaced with metal hand rails.