September, 2011

This material was filed under
[ Town Manager's Report ]
September, 2011

TOWN MANAGER’S REPORT Agenda Item
September 20, 2011

1. Intergovernmental Activity:
a. Melbourne Causeway: FDOT has proposed replacing the easternmost relief bridge (bridge number 700037) and the parallel pair of relief bridges (bridge numbers 700173 & 700175), which are east of the Ernest Kouwen-Hoven Bridge on US-192. The plan includes monies in FY-06 for design and monies in FY-10 for construction. For the tentative FDOT Five-Year Plan the construction cost has been projected at $15.7 million. A temporary bridge will be constructed south of the existing bridge, which will protrude about 45 feet south of US-192 along Douglas Park. Staff has requested that a separated 10-foot bike path be constructed on the bridges for traffic moving in both directions and four-foot bike lanes along the outer lanes of the new bridges. Preliminary plans provided by FDOT’s consultant on 2/28/07 reflect six-foot wide temporary bike/pedestrian bridges along the south side of the causeway south of the westernmost relief bridge and the easternmost relief bridge. The project proposes to have a five foot wide protected sidewalk along the north side of the westernmost relief bridge and an eight foot wide protected sidewalk along the south side of the easternmost relief bridge. A public meeting was held 6/11/07 at Eastminster Presbyterian Church. FDOT awarded the project to Johnson Brothers Contractors/Wilbur Smith & Associates with project to be completed by October, 2011. The permanent pedestrian bridge opened 7/1/10 and the lanes shifted north of it. Pile driving will no longer occur at night—only dawn to dusk. (09/16/10) Re-surfacing of pavement to occur in evening through August. (08/16/11)
b. US-192/SR-500: FDOT is considering adding to the Five-Year Tentative
Plan is FY-15 the resurfacing of US-192/SR-500 from Platt Street east to SR-
A1A, previously considered for FY-14. Consistent with Council action of
April 20, 2010, staff requested that FDOT resurface the side streets to Fifth
Avenue that are within the US-192/SR-500 right-of-way and consider
Whether a bike lane can be added to the outside lanes of US-192/SR-500,
Which FDOT believes is unlikely. (03/15/11) The project limits have been
shortened to end at the Ernest Kouwen-Hoven bridge rather than SR-A1A.
(08/16/11)
c. 2nd and Palm avenues: Council approved the County installing a sewer force main along portions of 2nd and Palm avenues in June, 2000. Work commenced by the County’s contractor, RKT, in October, 2001. Failures have occurred along the route of the pipe. The County sued RKT’s bonding company and recently won in court. However, the appeal period has not concluded yet. Staff is meeting with County personnel to ensure that the affected portions of 2nd and Palm avenues are returned to the Town’s standards. (10/19/10) RKT’s insurer has appealed the decision. (01/18/11) Court has set 7/7/11 as the date to receive the initial brief. (06/21/11)

Page Two
Town Manager’s Report

d. Post Disaster Redevelopment Plan: Staff is working with the County on a
unified Post Disaster Redevelopment Plan. This is a required item in the
Town’s Comprehensive Plan. (01/18/11)
e. Dispatch Services: The 2010 State Legislature approved a requirement that emergency dispatchers receive no less than 232 hours of training to be certified by October 1, 2012. (08/17/10)
f. SR-A1A Resurfacing: FDOT has included the resurfacing of SR-A1A north of US-192/SR-500 in the FDOT Tentative 5-Year Work Program for FY-14 at an estimated cost of $9.5 million. (01/18/11)
g. Florida Friendly Fertilizer Requirements: Staff is working with Brevard
County government as it works to ensure that all local governments have
Adopted fertilizer regulations consistent with the FDEP Model Ordinance.
The FDEP Model Ordinance has been revised since the Town adopted the
Regulations last April. (01/18/11)
h. Riverside Drive/US-192 Traffic: FDOT is reviewing the current situation whereby motorists on N. Riverside Drive that turn west onto US-192 after stopping on red sometimes do so conflicting with motorists on S. Riverside Drive, that have a green light, attempting to turn west onto US-192. (01/18/11)
i. Tower: The City of Melbourne is planning to remove the water tower on S. Palm Avenue. It has been reported that the system does not need the tower and the tower is deteriorating. (04/19/11)
j. Gun Regulations: The Town Attorney is to confirm that Council will need
to consider an ordinance repealing Sections 10-27 and 10-28 of the Town
Code in that the Town’s involvement in regulating guns has been preempted
by the State. (07/27/11)
k. Pedestrian Warning Signs: FDOT has been requested to install signs warning motorists to yield to pedestrians at the crosswalks at SR-A1A and US-192/SR-500 where they intersect. (8/16/11)
l. Sidewalk Repair: Brevard County has replaced sections of sidewalk at 105
N. Riverside Drive and at 1010 N. Palm Avenue. The broken sidewalk was
in the section of N. Palm Avenue that is outside of the Town’s boundary and along N. Riverside Drive, which is a County maintained street. (09/20/11)
m. Historical Marker: The application has been delivered to the Brevard Historical Commission for the historical marker to be installed in Nance Park recognizing the Indialantic Casino/Bahama Beach Club. The Heritage Committee prepared the application. (09/20/11)
2. Fiscal Activity:
a. Vests: The Police Department has ordered six replacement bullet-proof vests
with the grant paying one-half of the costs. Four vests were replaced in FY-
10. The vests last about five years. (08/16/11)

Page Three
Town Manager’s Report

b. Magnolia Pedway: The Town’s Zoning & Planning Board with the Parks, Recreation, & Beautification Committee held a joint public informational workshop on August 25, 2009 to address potential future development and use of the area from Eighth Avenue to Melbourne Avenue. The cost to prepare development plans is approximately $6,500. (12/16/10)
c. FEMA Firefighter Assistance Grant: The fire chief submitted an application for $45,838 Federal monies with a $2,412 local match for the following: $25,250 for 10 sets of bunker gear; $15,000 for Firefighting training for volunteers; and $8,000 for the cascade fill station to meet NFPA standards. (06/15/10) The grant application was not funded. (06/21/11)
d. Fire Truck Grant: The funding agency requested additional information and noted that the federal share amount has been reduced to $617,500 with the local share being $32,500. (01/18/11) The grant was approved and the matter goes to Council for approval. (03/15/11) Council authorized acceptance of the grant and approval to proceed toward the purchase of the ladder truck and have declared the 1987 FMC fire engine as surplus. (04/19/11) Council authorized the purchase of a truck from Crimson Fire, Inc. on 5/5/11. Chassis to be delivered 9/29 to Spartan and the ladder is currently being fabricated. (7/27/11)
3. Organizational Activity:
a. Pavers: The Town Centre Committee proposed a paver program at Indialantic Ocean Beach Park as a fund-raising effort. Council approved the sale of pavers on 9/16/10. (10/19/10) Jill Hoffman will present a marketing plan at the August meeting in order to progress with the project. (8/16/11) The Clerk has ordered the pavers. (09/20/11)
b. Indialantic Ocean Beach Park: Dune crossover #9 was closed until Public
Works could replace the rusted bolts that affix the stringers to the deck. The
improvements have been made. (09/20/11)
c. Nance Park: The showers adjacent to the restrooms were closed Friday,
September 9 through Monday, September 12 due to a leak. The leak has
been repaired. (09/20/11)
d. Signs: By January, 2012, the Town will need to ensure that all roadway
signs have been inventoried, regularly inspecting all roadway signs, and determine the method to address reflectivity of signs. By January, 2015, ensure that all regulatory roadway signs comply with the minimum reflectivity requirements. By January, 2018, ensure that all street signs comply with minimum reflectivity requirements. (03/15/11)
e. Swale: Public Works personnel installed a swale at 331 Ormond Drive and
at 408 Melbourne Avenue. (08/16/11)
f. Unionization: Negotiations with the Coastal Florida PBA are occurring as
the three-year agreement covering communications workers and police
officers expires at the end of the current fiscal year. (08/16/11)

Page Four
Town Manager’s Report

g. TMDL requirements: Staff is working with the Town’s engineering consultant to address Florida Department of Environmental Protection (FDEP) requirements for the Town to reduce TN (Total Nitrogen) and TP (Total Phosphorus). FDEP has not determined the amount of a reduction of TN and TP that will be required by the Town from the Town’s storm drainage system or the timeframe for compliance. FDEP is trying to determine that whuich the Town has accomplished with regard to meeting the Town’s goals/requirements; however, FDEP has so far not provided an indication as to what the Town’s requirements are and the Town’s engineer is uncomfortable in releasing information that could later be used to benefit the Town’s position. (10/19/10) The Town’s consulting engineer has determined that the Town is in compliance through 2012 based on the aggressive efforts of the Town to install swales within the Town’s rights-of-way. (04/19/11) The County is trying to engage municipalities in financially supporting gathering more detailed information with the expectation of lessening Federal/State required expenses. (09/20/11)
h. Unionization: The Florida Public Employees Relation Commission (PERC) has notified the Town that the six Town firefighters have petitioned to be represented by a union. Andy Hament, with Ford & Harrison, will respond to PERC on behalf of the Town. (05/17/11) Ballots should be received around September 20, 2011, which are to be counted on October 10, 2011. (09/20/11)
i. Mast Arm Signal: A motorist damaged the mast arm signal at the northeast
corner of SR-A1A and Fifth Avenue. The bell housing that protects the mast
arm post was broken. Public Works is in the process of replacing it, for
which a bill will be submitted to the motorist’s insurance carrier. (04/19/11)
Public Works personnel installed the replacement bell. (09/20/11)
j. Orlando Park: The pole climb piece of apparatus is being removed due to it
being unsafe. The wood has rotted, bolts have rusted, and metal climbing
items covered in plastic have rusted and are exposed. (08/16/11)
k. Orlando Park: A horizontal ladder has been installed within FY-11
budgeted funds to provide additional recreational options within Orlando
Park. (09/20/11)
4. Council Matters:
a. Trash Collection Days: WM assessed the impact of changes of service in
Palm Bay and Melbourne prior to implementing the change in collection days
as authorized by Council on August 17, 2010. The changes were proposed to
accommodate County landfill operation concerns. (03/15/11) A letter was
sent to customers noting the new collection days effective June 6, 2011.
(05/17/11) Waste Management reimbursed the Town for out-of-pocket costs
of $614 to send the notification to letters. (07/27/11)

Page Five
Town Manager’s Report

b. Sandspurs: The second application of a pre-emergent was applied to Town
parks in mid-April. The first application was in late February. (05/17/11)
c. Purchasing Cooperative: As previously noted staff is working toward possible participation in the Purchasing Cooperative with Brevard County and other municipalities. The cooperative is still in the formative stage with about four jurisdictions having agreed to participate thus far. It is not expected to be operational until sometime in calendar year 2012. (09/20/11)
d. Health Insurance Benefits: Staff is preparing a comparative list, as has been previously provided to Council, reflecting the level of support by various Brevard County municipalities for covering health insurance premium costs. (09/20/11)